Limit results
Trusted Advisor
Project
Stories
Events
Job Offer
No results found
TBF + Partner

Head of grounding Ceneri base tunnel

Ceneri, Switzerland

On behalf of the CPC consortium, TBF + Partner AG was commissioned with the earthing management. The earthing management covers all trades in the project (carcass, carcass equipment, construction power supply 50 Hz, track, catenary 16,7 Hz, power supply 50 Hz, radio, control system, safety systems).

In addition to the tunnel with 2 single-track tubes of 15.4 km each, the project perimeter also includes 48 cross passages, 5 technical niches, 9 sleeve chambers, the two railway technology buildings (BTG) in Vezia (south) and Vigana (north) as well as other surrounding buildings, the Vezia substation and the open lines.

The earthing management included the tasks of creating the return path and earthing concept, reviews with the planners, submission of the dossier to the BAV, installation instructions and checks, partial tests, measurements and the acceptance and overall verification of earthing.

Locations Switzerland

TBF + Partner AG
Schwanengasse 12
3011 Bern
TBF + Partner AG
Quai du Seujet 10
1201 Geneva
TBF + Partner AG
Via Besso 42
6900 Lugano
TBF + Partner AG
Beckenhofstrasse 35
Postfach
8042 Zurich

Locations Germany

TBF + Partner AG
Calwer Strasse 7
71034 Böblingen
TBF + Partner AG
Alsterarkaden 9
20354 Hamburg
TBF + Partner AG
Mauerkircherstrasse 9
81679 Munich

Location in Italy

TBF + Partner S.r.l.
Via Pola 11
20124 Milan